Published
March 14, 2017, 10:00 PM
To
upgrade the country’s power transmission network, the National Grid Corporation
of the Philippines (NGCP) announced that it was poised to undertake several
major facility improvement programs beginning this year, part of a five-year
program that is estimated to cost a total of P80 billion in capital investment.
“When we took over, it
was very clear to us that upgrading and improving the failing and aging
facilities we inherited from the National Transmission Corporation (Transco)
was top priority. At the time this concession was bid out, many of the
transmission facilities already reached, or were about to reach its maximum
economic life. It was very clear to us that government could no longer continue
to fund the massive transmission-related projects needed to ensure that the
transmission facilities remained relevant, up to date, and able to address the
pressing needs of a growing economy,” the company said.
“NGCP has built
2,472 circuit-kilometers (ct. km.) of transmission lines since we took over.
This year, 24 transmission projects are set to be completed, 26 are in the
middle of construction, and 22 projects will commence. In total, that’s an
additional 674.9 ct.km. of lines to be added to the country’s transmission
network for 2017 alone,” the company stressed.
Among the projects NGCP
is pursuing are: The Luzon 500kV backbone to accommodate incoming generating
plants, the Cebu-Negros-Panay backbone to improve power sharing between the
major islands, and the Mindanao 230kV backbone to reinforce the Mindanao grid
as new plants come online.
“Another aspect
of NGCP’s commitment is to ensure that all its facilities are well-maintained
and reliable. Our continuous auditing of existing assets has resulted in a
preventive replacement program designed to mitigate any unplanned transmission
outages. The program outlines the replacement of aging towers and poles
and substation equipment over the next four years,” stated NGCP.
For this year, the grid
operator is set to replace 2,134 wood poles that are considered grid
facilities, with steel structures. These wooden poles were part of the aging
transmission facilities NGCP inherited from Transco when it took over as
concessionaire in 2009. NGCP is also set to replace an additional 417
wood poles – considered residual sub-transmission assets – this year.
Facilities which serve to strengthen the network as a whole are considered grid
facilities, while those that serve a single entity or user, whether that user
is a power plant, a distribution utility or directly connected industrial
consumer, is considered a sub-transmission asset.
“Since 2009, NGCP
has installed a total of 13,200 megaVolt-amperes (MVA) of substation capacity.
Moving forward, over 30 transformers in substations across the country are also
set to be replaced between 2017 and 2019. Nine transformers with 300MVA,
100MVA, and 50MVA ratings located in critical areas such as Las PiƱas, San
Jose, and Naga, among others, are expected to be replaced this year alone.
That’s an additional 1,480 MVA in substation capacity over the next 3 years,”
NGCP announced.
No comments:
Post a Comment