Updated
By MYRNA M. VELASCO
The long delayed
650-megawatt (MW) Pagbilao gas-fired power facility of Energy World Corporation
(EWC) has already applied for certificate of compliance (COC) or its license
for the targeted commercial operations of the project.
The Energy Regulatory
Commission (ERC) disclosed that the COC application was filed by project
developer EWC April last year, although it has yet to make final notification
to the regulatory body on its testing and commissioning activities.
ERC chairperson Agnes T. Devanadera said the gas-fired power facility has not
been inspected yet, and she will be volunteering to do that task once the plant
tangibly reaches commissioning phase.
“I’ll be the one to do
the inspection,” the ERC chief told reporters, with her noting that based on
the last information the regulatory body has gotten, the plant does not have point-to-point
connection facility yet to underpin the transmission of its capacity to the
grid.
Devanadera indicated
that she will “look at all aspects of the project,” as there had also been
previous concerns that the port development as a component of the facility
might be traversing a “reservation area” proximate to the site of its liquefied
natural gas (LNG) terminal.
Sharon O. Montaner,
officer-in-charge of the ERC’s Market Operations Service (MOS) qualified that
EWC “applied for a COC, but we would still be notified before it reaches
testing and commissioning, so we are monitoring it. Then after testing and
commissioning, that’s the only time that we can do the inspection.”
The EWC project, which kicked off implementation in 2013, comprises of both a
power generating facility of 650MW that will be developed in phases; and an
onshore LNG terminal as facility support to its procurement of gas from
offshore.
As designed, the
facility was developed on a “pure merchant basis” – entailing then that the
project sponsor will be latching on trading its generated capacity at the
Wholesale Electricity Spot Market (WESM) as well as selling it to the
contestable customers or those end-users with usage thresholds already covered
by the Retail Competition and Open Access (RCOA) policy of the restructured
electricity sector.
For the longest time,
however, the project had hit roadblocks on the transmission facility connection
that will ensure its generated capacity would be wheeled to the main power
grid.
EWC secured government
help in resolving the project’s dilemma on the point-to-point connection
facility, but until last year, that has not been addressed.
No comments:
Post a Comment