Friday, August 27, 2021

Aboitiz to build transmission poles in Batangas

 

By Anna Leah E. Gonzales August 27, 2021

https://www.manilatimes.net/2021/08/27/business/top-business/aboitiz-to-build-transmission-poles-in-batangas/1812504

 

ABOITIZ Construction partnered with Lima Enerzone to construct overhead transmission poles in Lipa City and Malvar in Batangas to help stabilize power supply in the area.

In a statement on Thursday, Aboitiz said construction of the transmission poles will start in November and expected to be completed in six months.

The transmission poles will support 69-kiloVolt (KV) power lines that will supply power to businesses located in a 170-hectare Light Industry Science Park (LISP 4) and residential areas in a 212-hectare Pueblo de Oro in Malvar.

Lima Enerzone is a power distributor under AboitizPower Corporation that operates the distribution system of Lima Land, Inc. a Philippine Economic Zone Authority-registered economic zone in the Lipa City to Malvar area.

"In line with our mission to help businesses to thrive, Aboitiz Construction commits to deliver a quality and safe project for Lima Enerzone. Through this partnership, we aim to contribute to economic growth in Batangas by powering businesses and homes," said Levi Agoncillo, Aboitiz Construction's Vice President for Business Development, Tender Planning, Engineering, and Design.

Aboitiz Construction will handle the demolition and restoration of affected structures for the construction of the foundations and erections of steel poles. Cable stringing, clipping, and armoring will also be part of the transmission poles project.

Once completed, this project will provide a steady and reliable power supply in LISP 4 in order to support business operations, industries, and local services in the area.

Aboitiz said the project is part its initiative to enhance power delivery in Lipa City, Malvar, and surrounding areas, including Lima Technology Center through a partnership between Aboitiz Construction and Lima Enerzone.

Last January 2019, Aboitiz Construction commenced the design and construction of the 69-kV overhead transmission line project, which is expected to be completed this year.