Published December 20, 2016, 10:00
PM By Myrna
M. Velasco
MB File – The Malampaya gas field
uses an innovative and sustainable deepwater technology for recovering natural
gas from the deepwater reservoir in northwest Palawan. (Image from shell.com.ph
| Manila Bulletin)
That had been based on the initial
estimate of the utility firm, but subject to validation of the cost submissions
and assumptions on fuel shift resorted to by its contracted capacities that are
gas-fed.
The cost impact calculations will be
submitted to the Department of Energy (DOE) in a meeting that was convened by
the agency this Thursday (December 22) for all concerned and affected
stakeholders.
The gas facility will be on its
20-day maintenance downtime from January 20 to February 16 next year. Patently,
this is a shorter maintenance duration but the country’s biggest distribution
firm reckoned that it could still trigger rate hikes that will likely reflect
in March – in consideration of the billing lag time.
Meralco Spokesperson Joe Zaldarriaga
said “this may have an effect on the generation charge cost in March given that
the schedule will impact on the February supply month.”
He had not given figure on the
anticipated power rate hike, but industry sources hinted there are already rate
hike simulations drawn up by the utility firm.
Meralco said the upward power rate
adjustment may even be heftier if the proposed increase in fuel excise tax
(from currently at zero-percent level) will already be enforced within the
period.
For diesel, that will translate to
cost hike of P6.00 per liter and when the fuel is utilized for power
generation, the resulting increase in electricity costs will be at estimated
P1.50 per kwh for diesel-fired power plants. This then could be applied to the
Ilijan plant if it shifts fuel use to biodesel during the Malampaya shutdown.
There have been several plants that
came on-line since last year, but Meralco indicated the cost impact may not be
cushioned as much because the new capacities are also coming from gas plants.
Meralco Vice President Lawrence S.
Fernandez said “some of the additional supply is also dependent on Malampaya” –
like the San Gabriel and Avion plants of First Gen Corporation.
The most controversial shutdown
episode of the Malampaya gas production platform had been in 2013 – and that
ignited some sort of “social revolt” when Meralco’s rates had been up by P4.50
to more than P5.00 per kWh for two billing months.
The pass-on to consumers of the prohibitive cost
adjustments never happened though because of a restraining order issued then by
the Supreme Court.
No comments:
Post a Comment