By
Lenie Lectura - June 8, 2017
The National Grid Corp.
of the Philippines (NGCP) said on Thursday its comprehensive grid enhancement
program has helped prevent the occurrence of power failures during the last
summer period, just as when the demand for electricity is at its peak.
This year’s actual
electricity demand reached an all-time high of 10,054 megawatts (MW) recorded
on May 9 at 2:27 p.m. This surpassed last year’s actual peak demand and the
Department of Energy’s (DOE) 2017 peak demand projection
The total available
capacity in May was at 11,444 MW, allowing an operating margin of 1,390 MW.
According to the NGCP,
Luzon grid customers did not feel the effect of the steep rise in demand, as
improvements on the transmission facilities designed precisely to better manage
the grid during peak load periods were implemented by the grid operator in
anticipation of this year’s record-breaking power demand.
In particular, the NGCP
increased protection for its critical substation equipment, enhanced operating
measures of transformers at its San Jose, DasmariƱas, Bolo and Tayabas
500-kiloVolt (kV) substations, and coordinated adjusted capabilities of large
generating units, such as Sual, Masinloc, GN Power, Pagbilao, Ilijan and Santa
Rita/San Lorenzo.
Potential low voltage
problems were also eliminated through the timely energization of capacitor
banks, allowing the NGCP’s Luzon System Operations to maintain the system
voltage level within the normal limits, even at the height of the summer
season.
“The NGCP is pleased to
report that, through the foresight of our technical team, we were able to
prepare and address early on any potential grid stability issues for the summer
period, even as the demand breached the DOE’s projection. With this foresight,
our customers enjoyed reliable and uninterrupted quality of power,” the company
stated.
As the peak demand
season for 2017 nears its end, the NGCP seeks support for its projects aimed at
strengthening the grid for the coming years, as it also appeals for better
management of power supply, particularly scheduling additional energy sources
to increase the thinning supply.
“We want to be able to
accommodate the continually growing demand and supply for power in Luzon, not
just during the summer season. The support of local government units (LGUs),
government agencies, such as [the] DILG [Department of Interior and Local
Government], DENR [Department of Environment and Natural Resources], Laguna
Lake Development Authority [LLDA] and the public, will enable the NGCP to
complete these projects on time, if not ahead of schedule,” it said.
Part of the NGCP’s load
growth projects for Luzon are focused on reinforcing the Western and Eastern
Manila backbone, with critical components, such as the 230-kV Pasay Substation,
Taguig-Taytay 230-kV line and a 500-kV Taguig Substation.
“These locations have
been identified, through careful technical research and feasibility studies, to
be the most strategic, being close to the center of load growth. Delaying the
implementation of critical projects, like the Pasay substation, will lead to
overloading issues and possible power interruptions within Metro Manila,” it
said.
The NGCP is a
Filipino-led, privately owned company in charge of operating, maintaining and
developing the country’s power grid, led by majority shareholders Henry Sy Jr.
and Robert Coyiuto Jr.
No comments:
Post a Comment