By Lenie Lectura - August 9, 2019
THE LNG (liquefied natural gas)
project of First Gen Corp. has been declared as an “Energy Project of National
Significance” (EPNS) in accordance with Executive Order 30 (EO 30).
FGEN LNG Corp. (FGEN LNG), a wholly
owned subsidiary of First Gen Corp., said Thursday that its application for
EPNS declaration filed in June has been approved by the Energy Investment
Coordinating Council (EICC) through the Department of Energy (DOE).
EPNS are significant energy projects
for power generation, transmission and/or ancillary services including those
required to maintain grid stability and security, and which are in consonance
with the policy thrusts and specific goals of the DOE’s Philippine Energy Plan
(PEP).
FGEN LNG’s application for
declaration was submitted on the basis that its LNG project will require the
development of significant infrastructure and capital investment involving
complex technical processes and engineering designs that will result in a
substantial positive impact on the environment.
The LNG hub will be built in the
First Gen Clean Energy Complex (FGCEC) in Barangays Santa Clara, Santa Rita
Aplaya and Bolbok, Batangas City, under the management and ownership of FGEN
LNG.
FGEN LNG has completed significant
predevelopment work to make the project site “construction-ready.” It
broke ground on its LNG hub, estimated to cost from $700 million to $1 billion,
in May.
The project will be developed in two
phases. The first includes new unloading facilities for LNG carriers with
capacities ranging from 40,000 to 177,000 cubic meters; a 200,000-cubic-meter
LNG storage tank with a maximum sendout capacity of up to 5 metric tons per
annum (MTPA); two LNG truck loading bays; as well as provisions for a future
LNG carrier loading system for vessel capacities ranging from 5,000 to 40,000
cubic meters.
The second phase includes an
additional 200,000-cubic-meter LNG storage tank, increasing its sendout
capacity up to 7 MTPA; two additional LNG truck loading bays and an LNG carrier
reloading system.
The company targets to finish the
LNG terminal before gas from the Malampaya facility runs out in 2024.
First Gen already operates four
gas-fed power plants with an aggregate capacity of about 2,000 MW. These are
the 1,000-MW Santa Rita, 500-MW San Lorenzo, 414-MW San Gabriel and 97-MW
Avion.
The company said its LNG project
will play a critical role in ensuring the energy security of the Philippines
and the Luzon grid, particularly when the indigenous Malampaya gas resource no
longer produces sufficient fuel for the country’s existing gas-fired power
plants, and certainly not for additional gas-fired power plants.
“We would like to sincerely thank
the Department of Energy for approving our application for the FGEN Batangas
LNG Terminal Project as an Energy Project of National Significance.
“We believe that this project is
crucial to ensure the continued operations of the 3.2-GW existing natural
gas-fired plants given the expected reduction in gas supply from the Malampaya
field up to the expiration of the contracts by 2024,” said Jonathan Russell,
executive vice president and chief commercial officer of First Gen.
He added: “First Gen will continue
to work hard to ensure that this project will also be available to allow the
development of new gas-fired capacity, with a lower carbon footprint that will
support introduction of more intermittent renewables for the Philippines.”
First Gen has partnered with Tokyo
Gas Co. Ltd. for the LNG project. Both signed a joint
development agreement (JDA) in December last year.
The JDA is a preliminary agreement
between the parties to jointly pursue development of FGEN LNG project with
Tokyo Gas taking a 20-percent participating interest.
It said the project is also
consistent with both the DOE’s Nine Point Energy Agenda and PEP 2017-2040 as it
promotes liquefied natural gas importation as an option to supplement and
replace Malampaya gas.
FGEN LNG also received in March the
formal approval of its application for a Notice to Proceed from the DOE, as
defined in and required by the Philippine Downstream Natural Gas
Regulation.
No comments:
Post a Comment