Published
By MYRNA M. VELASCO
GNPower
Ltd. Co., which is a joint venture of the Aboitiz and Ayala groups, has
formally asked clarifications on the terms of reference (TOR) of the Manila
Electric Company’s (Meralco) competitive selection process (CSP) – primarily
the terms relating to “outage allowance” that shall be prescribed under the
power supply agreement (PSA) of the new plant capacity that shall be placed on
tender.
Atty. Jose Ronald V.
Valles, first vice president and regulatory head of Meralco, said “we intend to
file a letter to the DOE (Department of Energy) in response to the query made
by a prospective bidder with respect to replacement energy,” or the outage
allowance that will be accorded to the power plant that will be supplying to
the utility firm.
That particular query, he stressed, must first be addressed through a DOE
clarification before the utility firm can move forward on the publication of
its invitation to bid (ITB) for its targeted CSP for a 1,200-megawatt capacity
that will become part of its supply portfolio starting year 2024.
It was the energy
department that had just given its approval recently on the second revision on
the terms of reference (TOR) for the utility firm’s scheduled CSP this year.
Valles indicated “the
concern raised by GNPower was about the obligation for replacement power,” with
him emphasizing that the prospective bidder raises concern that it “cannot
afford to have zero outage allowance.”
The Meralco executive
emphasized the plea is “for 30 days scheduled maintenance and 15 days forced
outage allowance to be reflected in the TOR.”
Valles explained that under the existing power supply deals of Meralco, these
are “within the outage allowance,” and that the distribution utility “will have
the obligation to procure the replacement power and charge the replacement
power to consumers.”
However, beyond the
allowed duration of outages prescribed under the contract, “the generator will
have to procure that replacement power at (its) own risk.”
Meralco President Ray C. Espinosa said “the way the TOR is structured, the plant that will be awarded or the winning bid will have to be a new plant because the requirement is that a plant must not have achieved COD (commercial operation date) by 2020.”
Meralco President Ray C. Espinosa said “the way the TOR is structured, the plant that will be awarded or the winning bid will have to be a new plant because the requirement is that a plant must not have achieved COD (commercial operation date) by 2020.”
On the scheduled CSP,
Valles added that their third party bids and awards committee (TPBAC) is still
going over the revised TOR “and we wait for their advise as to when will this
be published.”
This is already the
second bidding for the utility firm’s solicitation of a new capacity that will
form part of its 2024 supply complement – the first one was in September last
year.
The company also
concluded last year the successful auctions on its PSAs for brownfield
capacities for baseload and mid-merit requirements – and the contracted plants
have already started delivering power to it last December following the
approval of the contracts by the Energy Regulatory Commission.
No comments:
Post a Comment