By Lenie Lectura - March 10, 2020
The Manila Electric Co. (Meralco) is
likely to release this week the revised terms of reference (TOR) for the
competitive bidding of a 1,200-megawatt (MW) power supply contract.
“I hope we can publish this week,”
said Meralco President and CEO Ray Espinosa in an interview on Monday when
asked for an update of the competitive selection process (CSP), which has been
postponed in the past because the Department of Energy (DOE) strongly urged
Meralco to relax the TOR in order to attract more participants.
Espinosa said the last issue to be
ironed out, which concerns replacement power and outage allowance, was already
cleared by the DOE.
“It’s ok with them. There is still
outage allowance. They understand it,” said the Meralco official.
Meralco earlier raised to the DOE
the concern of one of the bidders, GNPower.
“The concern raised by GNPower was
about the obligation for replacement power. They are saying that the generator,
prospective bidder, cannot afford to have zero outage allowance. They are
asking for 30 days scheduled maintenance and 15 days forced outage allowance to
be reflected in the TOR,” said Espinosa.
The DOE had wanted to impose zero
outage to protect consumers from spike in electricity prices.
“We’re raising it to the DOE because
they required it, they have their reasons but the bidders are saying, what
about the investors, the power supplier. It was a commercial industry practice
before it was changed by the DOE,” he said.
In the previous power supply
agreements of Meralco, Espinosa said it is Meralco’s obligation to procure the
replacement power and charge that replacement power to consumers within the
30-day and 15-day outage allowances. Beyond outage allowance, the power
generator is responsible to procure that replacement power at its own risk,
explained the Meralco official.
Espinosa said he is pleased with the
outcome of the revised TOR. “That’s why it became important to work out a good
terms of reference so we’re able to attract more bidders. I think we have a
balance and good TOR already, subject to only one clarification, which relates
to the replacement power, obligations related to outages. After that, we should
be good to go.
We’re confident that with the way
the TOR has developed, it will be looked at by potential bidders as good terms
of reference and should attract a good number of qualified, serious bidders.”
Among the other revisions include
the stacking of capacity of several power plants to meet Meralco’s 1,200-MW
supply requirement and include merchant power plants to participate in the CSP.
It can be recalled that when Meralco
first conducted the CSP for the 1,200-MW greenfield capacity only new power plants
were allowed to participate.
Back then, the bids and wards
committee declared a failed bidding after only Atimonan One Energy Inc., a unit
of Meralco Powergen Corp., submitted its offer. After which, the DOE told
Meralco that it must include old and new power plants.
No comments:
Post a Comment