By
Lenie Lectura- April 30, 2019
THE chairman of the
country’s largest power-distribution firm warned on Monday that the country
would continue to experience power shortage in the next few years unless more
capacity is added to the grid.
“The continuing yellow
and red alerts being experienced today may eventually lead to serious power-
supply shortage in the next few years, unless immediate action is done to
resolve the root cause of the problem, by adding more generating capacity and
taking decisive action on the much-delayed construction of new power plants,”
said Meralco Chairman Manuel Pangilinan.
Meralco’s seven
power-supply agreements entered into with various power supplies have yet to be
approved by the Energy Regulatory Commission. The approval of the PSAs is
crucial because the project proponents could not start construction until the
ERC gives its green light.
Atimonan One Energy
Inc.’s first 2x 600-megawatt (MW) power plant, which was already certified as
an Energy Project of National Significance, awaits ERC approval. It was filed
on April 29, 2016.
Meralco PowerGen (MGen)
Corp., the power-generation arm of Meralco, noted that if this power project
had been approved on time, then at least 600 MW would have been added to the
grid this year.
“We have already
reached in April the peak demand level that was recorded in May last year. At
least 626MW is needed and this is just about the estimate that the DOE keeps on
saying. So, the DOE is right in saying that we need new capacity of 600MW every
year as demand keeps rising,” noted MGen President Rogelio Singson.
Pangilinan said that
while the private sector continues to heed the government’s call in putting up
capital-intensive power projects, industry players could not stress enough the
support they need from the regulators.
“I could say I was
vindicated but it does not change the situation. So, we just address the
current situation…I am afraid I’d get criticized for saying this: This is going
to be with us for next two to three years,” said Pangilinan.
He urged the government
to “get their approval processes done as quickly as they can” so that consumers
won’t suffer from power outages and high electricity costs.
“I don’t understand,
that’s the money of the private sector…. Let the people who have the means and
reasons for building power plants, be it coal or gas, to build the capacity. I
really don’t know what they are looking for. Sigurado, mangyayari na naman ito
[For sure, this will happen again] next year,” warned Pangilinan.
Pangilinan was
referring to the rotational brownouts that hit Luzon this month.
Eighth red alert
For the eighth time
this month, the Luzon grid was placed on red alert on Monday. A red alert
notice is raised when there is severe power deficiency and zero contingency
reserve. When the red alert is issued, power interruptions are expected to
happen.
“We are still on red
alert today. In fact it’s already the eighth day of manual load dropping that
Meralco has been doing since April 10. One of the reasons for the deficiency is
there are still three plants in Bataan that are still isolated from the grid,” said
Meralco Head of Networks Ronnie Aperocho.
The GN power unit 2 and
the two units of the San Miguel plants in Limay are still offline, following
the 6.1-magnitude earthquake that hit Luzon last week. These three plants have
a combined capacity of 660MW.
“Our forecast is even
if these three plants would be able to go back to the grid because of the
increasing power demand during the summer months, especially next month, we
still see several days of yellow and red alert and will even, in fact, extend
until the month of June,” said Aperocho.
The recent spate of
yellow and red alerts signal an increase in spot market prices. In fact, the
market operator said that the secondary price cap was triggered twice in the
April supply month, which implied that there were sustained high prices in the
market.
“While we are
anticipating lower coal and natural gas prices from IPPs and PSAs, these maybe
more than offset by the higher spot prices, which we will see as a higher
generation charge this May,” said Meralco Head of Utility Economics Lawrence
Fernandez.
The ERC, for its part,
has been saying that the only time it can act on the pending PSAs is when the
Supreme Court has decided on the case.
“The problem is nasa
[with] SC. Wala kami magagawa [There’s nothing we can do]. Hope the SC will be
compelled to act on it,” said Pangilinan.
No comments:
Post a Comment