Published May 5, 2019, 10:00 PM By Myrna M.
Velasco
Power distributor Manila Electric
Company (Meralco) has forked out over P12 billion capital expenditures (capex)
as of March this year for various projects particularly network reinforcement,
as well as relocation of facilities being traversed by various infrastructure
projects of the government.
Of the amount, Meralco indicated
that it spent P5.14 billion for new customer connections; P2.22 billion for
addressing load growth and P3.51 billion for asset renewals. Meralco sets its
capex covering regulatory year July to June of the following year.
Meralco Chairman Manuel V.
Pangilinan said the company “remains committed to investing the requisite capex
to continue improving its distribution infrastructure of services, for
conventional and renewable generation, as well as for value-adding businesses
complementary to our core electric power business.”
Company President Oscar S. Reyes
further indicated that part of the utility firm’s network improvement will be
making its facilities smarter and customer-friendly, so it can serve customers
better in a highly digitized world.
“While network facilities remain to
be hard assets taking up large parcels of land or vertical spaces of a
building, Meralco’s network and customer-facing infrastructure platforms and
systems are much smarter today and will become more so with continuous
innovation and incorporation of digital options.”
He stressed, “In this rapidly
changing environment, it is imperative that we always be ahead of the curve and
be unrelenting in our delivery of the best customer experience through our
capex execution.”
Among the capex projects pursued
have been the development of the Southwoods 115-kilovolt-34.5kV substation; the
construction of the San Jose delivery point’s additional 115kV line; and the
development of the Calamba 230kV substation.
Further, the utility firm replaced
167 overloaded distribution transformers – partly also to address load growth
within its network.
Meralco also set expansion of its
Filinvest 115kV-34.5 GIS substation as well as the installation of Zapote (Las
PiƱas) 5th 300-megavolt ampere power transformer; as well as other substation
and network upgrade projects.
In addition, the company shelled out
massive capital outlay for ventures that will underpin the government’s “Build,
Build, Build” infrastructure development paradigm.