Danessa
Rivera (The Philippine Star) - December 27, 2019 - 12:00am
MANILA, Philippines —
Manila Electric Co. (Meralco) has relaxed its rules on the second round of the competitive
selection process (CSP) for 1,200-megawatt (MW) greenfield capacity
required by 2024.
Under the terms of
reference published, power players can offer contract capacity at 600 MW
blocks, and can bid using multiple units with a minimum capacity of 150 MW per
unit and the same fuel type.
Bidders can offer fuel source “from a technology that complies with the
prevailing emission standards under pertinent (Department of Environment and
Natural Resources) DENR issuances on emission and other environmental standards
for power plants.”
For the contract, there
will be no outage allowance provided.
This means if the power
supplier fails to make available the contracted capacity, it will be fined
equivalent to P908 per affected megawatt-hour (MWh) nomination by Meralco,
which shall be used to reduce the generation charge to the consumers.
If the power supplier fails to meet the commercial operation date (COD), the
power supplier should procure replacement
power to be paid for by
Meralco at the lower between the wholesale electricity spot market (WESM) price
and the contract price.
Meralco is seeking bids
for 1,200 MW with supply for 20 years starting September 2024.
However, the power
distributor has the option to take available energy up to 1,200 MW (net) “at
commissioning energy charge” starting September 2023.
Meralco said supply
should come from a baseload (firm and dispatchable) power plant.
Meralco reserves the
right to reduce the contract capacity “equivalent to the reduction in the
demand of captive customers in order to avoid stranded contract capacity or by
reason of the implementation of Retail Competition and Open Access, the
Renewable Energy Law, or other Laws and Legal Requirements.”
Interested parties are
required to submit an expression of interest and confidentiality undertaking
until Jan. 13, 2020 to participate in the CSP.
The TPBAC has set a
pre-bid conference on Jan. 20 and the bid submission deadline on Feb. 17.
Last September, Meralco
conducted the CSP for the 1,200-MW greenfield capacity. It was declared a
failed bidding after only Atimonan One Energy Inc., a unit of Meralco Powergen
Corp. (MGen), submitted its offer.
After the failed
bidding, the Department of Energy (DOE) directed Meralco to open the second
round of its CSP to all power plants—whether old or new—to truly allow
competition and get the least cost of power for consumers.