By Lenie Lectura - April 18, 2017
THE Energy Regulatory Commission
(ERC) has allowed the National Grid Corp. of the Philippines (NGCP) to proceed
with its proposed transmission-backbone project in Mindanao costing P6.6
billion.
In a 20-page order, the ERC said
NGCP’s application for the approval of the upgrading of the Mindanao
230-kilovolt (kV) transmission backbone project is in accordance with the
provisions of the Electric Power Industry Reform Act of 2001.
“The approval of the project will
redound to the benefit of its customers in terms of continuous, reliable and
efficient power supply,” the ERC said.
The total cost of the project is
P6,591,741,669.50. It would have two major components. These are the
Matanao-Toril-Bunuan 230-kV transmission line and the
Baloi-Villanueve-Maramag-Bunuwan transmission line. The NGCP said there is a
need to upgrade the existing facility because it could not cater to the full
dispatch of additional power-generation capacity coming from new power plants
put up in the region.
“Only a limited amount of power can be
dispatched in order to maintain the reliability of the system,” it said. Should
all the power plants in Southern Mindanao be fully dispatched, NGCP foresees
the power plants located in Northern Mindanao cannot be dispatched in their
maximum capacity and the Davao-Bunawan transmission line and transformers in
Bunawan substation will be overloaded.
The following are the power plants
in the northern portion of Mindanao: FDC Corp.’s Units 1-3 (135 megawatt each),
which are all under commissioning stage, and GN Power Coal’s 450 MW and 150 MW
which have yet to start.
In the scenario all power plants
located in Northern Mindanao will be fully dispatched, the NGCP foresees the
following consequences:
The power plants cannot be
dispatched in their maximum capacity, the transformers will be overloaded, and
there could be voltage violations.
The following are the power plants
in Southern Mindanao: Units 3 and 4 (150 MW each) of Therma South, four units
(150 MW each) of SMC Davao and two units (105 MW each) of Southern Mindanao.
In its order, the ERC required NGCP
to pay a permit fee of P49.43 million.
No comments:
Post a Comment