By:
Ronnel W. Domingo - :28 AM April 01, 2017
The power supply
situation in Luzon will be “stable” in the next eight weeks with a gross
reserve of at least 1,350 megawatts in generating capacity available at the
time of the year when demand peaks, according to the National Grid Corporation
of the Philippines.
“Demand is forecast to
peak this year in the week of May 13 to 19 at 9,870 MW,” said Fidel D. Dagsaan,
head of NGCP’s power network planning division.
Dagsaan said in a press
briefing that available generating capacity was 11,220 MW and this did not yet
include new capacity that might go online during summer.
According to the
Department of Energy, at least two generators—both from the San Miguel group
and representing a combined capacity of 300 MW —were expected to start
commercial operation in the next two months.
Dagsaan said that
electricity demand in Luzon has peaked— for this year so far—at 9,549 MW last
week.
“Last year, demand from
Luzon peaked at 9,726 MW in the third week of April,” he said. “This means an
increase of 8.9 percent from the 8,928 MW peak demand in 2015.”
Also, the forecast peak
demand for 2017 represented an increase of 1.5 percent over last year’s actual
reading.
NGCP spokesperson
Cynthia P. Alabanza said the power supply situation was better in the Visayas
and Mindanao.
“Demand in Mindanao
usually peaks in December and in the Visayas it is still another time of the
year,” Alabanza said. “The situation is different from Luzon. Mindanao even has
an oversupply.”
No comments:
Post a Comment