Published January 24, 2017, 10:01 PM
By Myrna M. Velasco
With the Department of Energy (DOE)
stepping up its review of the “validation data” on completion of solar farm
developments under the second wave feed-in-tariff (FIT) race, more “data
defects” are getting exposed for those projects that were given certificates of
endorsement (COEs) for subsidy availments.
Data culled relating to the
mandatory registration of projects with the Wholesale Electricity Spot Market
(WESM) had shown some of the flaws and violations that could have disqualified
some endorsed projects in the FIT race or the subsidy scheme from consumers’
pockets that could guarantee the revenue stream of solar projects for the next
20 years.
If “data inconsistencies” in the
FIT-backed solar projects would not be rectified, some project developers could
just be basking in the spoils of regulatory mishaps and would be laughing their
way to the banks – but to the misfortune of the exploited Filipino consumers.
As a matter of policy, solar power
projects are required to register with the WESM and this is also a primordial
requirement before they can set their ‘first dispatch’ and be validated for
commercial operation date (COD by the Renewable Energy Management Bureau (REMB)
of the energy department.
On this requirement alone, three
solar projects with approved FIT certificates of compliance (COCs) were found
to have registration with WESM later than their declared commercial operation
date – which could have been violation of the rules of the FIT race.
These include the 2.04-megawatt Lian
solar power project that had certified commercial operation date (COD) of March
8, 2016 but was only registered with the WESM on March 10, 2016; the 10.26MW
Cabanatuan solar power project with COD on March 11, 2016 but its official registration
with WESM only happened on March 15, 2016.
Another project, the 5.02MW Palauig
solar power project had similar dilemma of WESM registration on March 15, 2016;
but its COD was supposed to have been achieved earlier on March 13, 2016.
Relevant industry sources explained
that those projects could not have been accorded validation for “commercial
operations date” without first securing their WESM registration, because that
entailed non-readiness to sell their generated electricity.
Affected players in the solar sector
also raised to the DOE their complaints that two projects were sparingly
granted fast-track accommodation on the award of their FIT certificates of
compliance (COCs). These are the 10.26MW Cabanatuan and 63.3MW Calatagan solar
farm ventures which were awarded FIT-COCs on March 11 and 14, 2016
respectively; while the rest of the “race participants” waited until June 10
last year or three months after the prescribed March 15, 2016 cut-off before
they were informed as FIT qualifiers.
The award of the latest FIT-COCs for
17 solar projects under FIT2 race had been controversy-ridden because of
perceived regulatory cataclysm – primarily because the Energy Regulatory
Commission (ERC) had not waited on the outcome of the data revalidation being undertaken
by the DOE and their action had just been based primarily on a request of the
National Renewable Energy Board (NREB), an entity which is not the proper
authority to defend the authenticity and veracity of data validation in the
DOE’s certificates of endorsement.
No comments:
Post a Comment