By
Lenie Lectura - February 1, 2017
THE National Grid Corp.
of the Philippines (NGCP) on Wednesday released the results of a
study that will interconnect the Visayas and Mindanao grids.
“The NGCP is pleased to
report we already finished the hydrographic survey that will determine the
route of the Visayas-Mindanao Interconnection Project. With this development,
we now have a clearer plan on the project’s implementation. Power-resource
sharing between the country’s major islands will now become a reality,” the
grid operator said.
In an NGCP-commissioned
hydrographic survey conducted from September to November 2016, a viable route
along the country’s western seaboard—beginning in Cebu and terminating in
Dipolog—was determined as viable for the implementation of the plans of
interconnecting the Visayas and Mindanao grids.
The project is envisioned
to be finished by 2020, assuming all regulatory approvals are secured on time.
The Luzon and Visayas
grids have long been connected via NGCP’s Naga-Ormoc High Voltage Direct
Current line.
Previous feasibility
studies conducted by the National Power Corp., one dating back to as early as
1984, were deferred by the government, then the grid operator. An earlier
study conducted by NGCP revealed eastern routes as unsuitable for submarine-
cable ground laying because of a significant quantity of live ordinance—torpedoes
and high explosive shells—from the Battle of Surigao in 1944, an underwater
volcano, fault lines and seismic hazards, such as unstable rock slabs that can
cause landslips and tsunamis.
With the hydrographic
survey result, the NGCP will now proceed with the preparation of a conceptual
design, detailed cost estimate and update of system-simulation study using the
Cebu-Dipolog route, in order to complete documents needed when it filed its
application before the Energy Regulatory Commission in April this year.
Inland and route
surveys for substations and associated overhead transmission lines will also
coincide with the preparation of documents. Barring unforeseen circumstances
and unavoidable delays, the project is estimated to be completed by December
2020.
“We need the support of
the government, the Energy Regulatory Commission, the Department of Environment
and Natural Resources and the different local government units the project will
traverse, among others, to push this forward. With their full support, we are
confident we will be able to complete this project on time,” the company said.
The NGCP is a privately
owned corporation in charge of operating, maintaining and developing the
country’s power grid. It transmits high-voltage electricity through “power
superhighways” that include the interconnected system of transmission lines,
towers, substations and related assets.
The consortium, which
holds the 25-year concession contract to operate the country’s
power-transmission network, is comprised of Monte Oro Grid Resources Corp., led
by Henry T. Sy Jr.; Calaca High Power Corp., led by Robert G. Coyiuto Jr.; and
the State Grid Corp. of China as technical partner.
No comments:
Post a Comment