By
Lenie Lectura - October 31, 2018
THE
Manila Electric Co. (Meralco) has considered the option of converting the
shovel-ready $3-billion Atimonan One Energy (A1E) coal-fired power plant into a
merchant facility or power plants that do not have long-term power purchase
agreements to cover their output.
The
utility firm is optimistic the regulators would soon approve the power supply
agreement (PSA) application it entered into with
A1E. The PSA approval is necessary before the project proponent can financially
close the project and commence construction. This is because lenders require
projects to present an approved PSA before extending loans to energy
developers.
However,
the utility firm’s chairman is not discounting the possibility that the power
project may be converted into a merchant plant.
“Yeah,
why not? It’s only money,” replied Meralco Chairman Manuel V. Pangilinan when
asked if the Atimonan power plant can be converted into a merchant plant.
“We have
given the greenlight to management to proceed with Atimonan. At first, we gave
the limited notice to proceed, but eventually when they start shoveling, we
will give them a notice to proceed. We don’t want Atimonan to fall by the
wayside like Redondo,” Pangilinan said.
More
than two years since the PSA between A1E and Meralco for A1E’s 2×600 megawatt
(MW) plant was filed, A1E continues to await approval from the ERC. On August
30 A1E filed with the ERC its fourth “very urgent motion” to resolve its PSA,
highlighting significant negative impacts to the overall project in terms of
total project cost, timetable and eventual power prices, as well as the
country’s power situation.
All the
necessary agreements, particularly the EPC (engineering, procurement and
construction) and loan agreements, are in place.
Financing
has been arranged by the mandated lead arrangers and bookrunners with a mandate
letter signed with a consortium of eight local banks.
Transmission right-of-way acquisition is currently close to full completion.
Meralco
PowerGen Corp. (MGen), the power
generation arm of Meralco, said the option to convert it into a merchant plant
is being considered as a last option.
“There
are other options such as to go into competitive selection process first. We
can go merchant also, but that’s the last resort,” MGen President Rogelio
Singson said. “We will assess whether to go merchant or not.”
As
delays hound the power project, Singson cited ballooning costs.
Of the P150-billion project cost, Singson said P107 billion will be funded via bank
loan.
“There’s
a P3-billion interest per year. Since the time we negotiated until today, there
is a 3-percent increase every year,” Singson said.
Meralco
President Oscar Reyes also cited adjustments in the exchange rate, another major
factor in determining the project cost.
“Project
cost has significantly increased because of the exchange rate. At the time we
filed, the rate was between 46 and 48. Now, it’s 53 to 54 to a dollar. Interest
rate at the time we filed was low at below 4.4 percent. Now, it’s up by at
least 3 percent. It’s P3 billion a year on the P107-billion loan and
construction period of about 42 months. We still remain focused though,” Reyes
said.
A1E is a
2×600 MW greenfield, ultra-supercritical pulverized coal-fired plant in
Atimonan, Quezon, the first ultra-supercritical plant in the country.
Completion of the first 600 MW is targeted by the third quarter of 2023, and
the second unit by the first quarter of 2024.
No comments:
Post a Comment