By Lenie Lectura - July 19, 2019
Consumer group Laban Konsyumer Inc.
(LKI) strongly urged all power-generation companies (genco) to participate in
the bidding of power supply requirements via competitive selection process
(CSP) of distribution utilities (DUs) to assure the country of adequate and
affordable power supply.
“There should be the participation
of all power suppliers. CSP allows for the bidding of all power generators. The
more power plants, the better…it is not the time to block power generators from
bidding. We must encourage all interested parties to participate in CSP and
bidding to save our country from a power situation crisis,” said LKI President
Victor Dimagiba.
At the same time, LKI called on all
DUs and electric cooperatives to immediately conduct and implement a
CSP in procuring their power supply requirements following the recent Supreme
Court decision that required all power supply agreements (PSAs) forged
after June 30, 2015, to undergo CSP.
The CSP requires DUs to
hold competitive bidding for their supply requirements as against securing
power deals via bilateral contracts. This is meant to ensure transparency
and fair competition.
LKI agreed with the Department of
Energy (DOE) in saying that all affected power industry players must catch up
and push under the CSP those stalled supply agreements in a bid so as to ensure
adequate power supply at the least cost to meet the growing
electricity demand of the country.
“It is imperative that we
add to our current power supply situation. Unfortunately,
we have had more red and yellow alerts this year than in the past five years.
We are already more than three years too late according to our
energy timetable.
“It is important that CSP is
undertaken and implemented immediately, and invitations to all bidders begin.
The CSP process will ensure that the much-needed power supply will be provided
at the least cost possible, which will, in turn, benefit consumers. CSP itself
was designed to ensure the best bids and the least costs to the consumers.
We can no longer afford any further delay. We need to act now with extreme
urgency to make up for the lost time,” said LKI.
The Manila Electric Co. (Meralco)
has already published three bid invites for its power requirements totaling
2,900 megawatts (MW).
Over 90 PSAs, with about 5,000 MW
capacity, were affected by the SC decision. Of which, 70 percent of the
affected PSAs are from Meralco.
No comments:
Post a Comment