By
Lenie Lectura - July 29, 2019
THE renewable-energy
(RE) unit of PetroEnergy Resources Corp. (PERC) is allotting as much as P2.7
billion to expand the solar and wind portfolio of PetroGreen Energy Corp.
PetroGreen Vice
President and Chief Operating Officer Francisco Delfin Jr. said the company
plans to put up 10-20 megawatts (MW) of solar power capacity in Palawan costing
“a little over P1 billion, about P1.1 billion to P1.3 billion.”
Delfin added:
“This is a service contract we secured as early as 2017. We have already
secured many of the necessary government permits including LGU endorsements,
ECC clearances. We have completed the technical feasibility studies. The only
thing holding us back from proceeding is the off-taker in Palawan.
There’s only one buyer and that is Paleco [Palawan Electric Cooperative].
We are are still waiting.”
In order for the
company to supply Paleco, the electric cooperative (EC) must first
conduct a competitive selection process (CSP).
The CSP requires
distribution utilities and ECs to hold competitive bidding for their
supply requirements as against securing power deals via bilateral
contracts. This is meant to ensure transparency and fair competition.
The plan is to put up
10 to 20 MW of solar power on a property that is already owned by PERC.
The power facility will also include diesel and battery storage for continuous
power supply throughout the day. Delfin said the solar power project could
be constructed in phases, depending on the requirements of Paleco.
When it will conduct a
CSP “all depends on Paleco,” he said. “We can go with an initial 10 MW,
but it depends on the customer. The diesel component will ensure the 24-hour
availability. For the battery, we are looking at two to four hours of battery
storage hours.”
PERC, through it
renewable-energy holding unit PetroGreen, operates four power-generating
units—the 20-MW Maibarara-1 and the 12-MW Maibarara-2 geothermal plants under
Maibarara Geothermal Inc. (MGI), the 36-MW Nabas-1 wind farm by PetroWind
Energy Inc. (PWEI), and the 50-MWDC Tarlac-1 solar plant under PetroSolar Corp.
(PSC).
Last
week, Delfin said PWEI will expand its 36-MW Nabas wind power project
by 14 MW for P1.4 billion.
The target commercial
operation of the expansion project is first quarter of 2021.
Delfin added that the
target completion of the wind expansion project depends on the completion of
various transmission line projects of the National Grid Corp. of the
Philippines (NGCP) in the area. Without transmission lines, power from the
impending Nabas 2 project cannot be delivered to an electric cooperative
which, in turn, will distribute electricity to the households.
Aklan’s electricity
demand currently stands at 61 MW, half of which comes from Boracay Island.
Delfin said that the
project’s target completion date also depends on how fast it can procure a
power-supply contract with a distribution utility firm.
Aklan Electric
Cooperative distributes electricity in Aklan. PWEI is eyeing to supply power to
Akelco via CSP.
“Our target is Akelco.
With the cleanup of Boracay, hotels and establishments are going back to Akelco
rather than operate their own generator sets. Our proposition to them is that
by sourcing their supply from Nabas, it will not only stabilize Akelco’s
distribution system but also promote investments compared to sourcing from
outside Aklan,” explained Delfin.
No comments:
Post a Comment