Published July 19, 2019, 10:00 PM By Myrna M.
Velasco
With several power supply agreements
(PSAs) expiring this year, power utility giant Manila Electric Company
(Meralco) is soliciting PSA tenders for aggregate capacity of 2,900 megawatts
both from existing power facilities and then greenfield projects due to come on
stream by year 2024.
For Filipino consumers to really
benefit from “lowest cost power supply,” Laban Konsyumer, Inc. (LKI) President
Vic Dimagiba is calling on all power generation companies (GenCos) to make
offers in the three sets of competitive selection process (CSP) that Meralco
has been scheduling for its power supply procurement.
“The CSP process will ensure that the
much-needed power supply will be provided at the least cost possible, which
will in turn benefit consumers,” the former trade and industry official noted;
adding that the CSP itself “was designed to ensure the best bids and the least
cost to the consumers.”
The 2024 requirement of Meralco will
be for 1,200MW base load capacity and that is being auctioned this year within
the purview of the CSP policy guided by the Department of Energy’s circular and
as upheld recently in a ruling of the Supreme Court.
The bulk of power supply deals due
for competitive bidding will be to replace its contracts falling due this year
and in the coming years. So far, three CSP tenders had been scheduled by the
power firm for its new PSAs.
For the greenfield capacity, the
power firm has factored in the gestation period of new power plant projects –
which normally takes 4-5 years from permitting to securing financing; tapping
engineering procurement and construction (EPC) contracts up to the actual
construction and advancing the plant to commercial operations.
Under the Power Supply Procurement
Plan (PSPP) submitted by Meralco to the DOE, it was shown that three more PSAs
will expire in December this year; while another one already lapsed in May.
The major PSA maturing in December
is for the 1,065-megawatt contracted capacity from the Ilijan gas-fired power
facility with South Premiere Power Corporation (SPPC) of the San Miguel group –
the plant of which has been catering to the baseload and mid-merit capacity
needs of the power utility company.
The others are the 250MW contracted
capacity from the Pagbilao coal plant of Therma Luzon Inc. of the Aboitiz
group; and the 260MW PSA-underpinned procurement from the Masinloc coal plant
acquisition of the San Miguel group. Both plants serve the base load capacity
requirements of Meralco.
The contracts that already expired
had been those of Philippine Power and Development Company (an embedded
facility); the PSA with Therma Mobile Inc. of the Aboitiz group but was renewed
with interim power supply agreement (IPSA) during this year’s summer months;
plus the one with Sem-Calaca power facility of the Consunji group which had
also been set for renewal. The rest of the PSAs that had fallen due had been
with Panay and Toledo plants and the 1890 Energy Corp. plant which all catered
to the peaking capacity needs of Meralco.
For its future power requirements
that will be supplied by prospective PSAs from greenfield or new-build power
facilities, Meralco noted that such had been anchored on forecast demand growth
mainly of its captive end-users or the segment of consumers that has to be
continually served by their franchised distribution utilities.
From the utility firm’s captive peak
demand of 5,658 megawatts in 2019; that is seen rising to 6,557MW in 2024 or an
increase of 899MW plus the increasing supply needs also of the commercial and
industrial end-users that it will be continually serving. Based on the
company’s projections, demand growth will reach as high as 1,059MW in 2024; and
will climb higher to 1,110MW in 2028.
In its forecast of coincident peak
demand, Meralco noted it factored in franchise demand growth rate of
2.76-percent and has likewise taken into account the pace of migration of
contestable customers.
The contestable end-users are those
customers that can already exercise their freedom of choice in contracting
their power supply with their preferred electricity suppliers – being the
mandate under the Retail Competition and Open Access (RCOA) policy as
sanctioned by the Electric Power Industry Reform Act for the liberalized power
sector.
No comments:
Post a Comment