By Lenie Lectura - July 16, 2019
THE Manila Electric Co. (Meralco) is
again soliciting bids for its power requirements, another 1,200 megawatts (MW)
of capacity, via a Competitive Selection Process (CSP).
This is Meralco’s second published
bid invite, following a Supreme Court decision that required all power supply
agreements (PSAs) forged after June 30, 2015, to undergo CSP.
Based on the terms of reference
published on Monday, a 20-year power supply contract, from September 2024, is
up for bidding on September 10.
The 1,200-MW capacity must be
supplied by any baseload power plant, one that usually provides a continuous
supply of electricity throughout the year with some minimum power generation
requirement. Baseload plants will only be turned off during periodic
maintenance or upgrading.
The power plant should achieve
commercial operations not earlier than March 2024 for the first unit, with full
contract capacity by September 2024. In case the plant has four units, two of
these must attain commercial operation date (COD) by March 2024.
If there is a delay in the COD,
Meralco may terminate the PSA and forfeit the performance security. Other
grounds for PSA termination include event of default, nonfulfillment of
condition to effective date, certain events of force majeure, expiration of
term, upon mutual agreement and change in circumstances.
The power plant must be located in
not more than two plant sites and with one delivery point within the Luzon grid
and nearest to Meralco’s load center. Should there be multiple units, the
minimum capacity per unit is 300 MW. Meralco requires that the capacity of the
plant must not be contracted with any other plant.
Also, the power plant that will
supply Meralco must not experience more than 30 days of scheduled power outage
and not more than 15 days of forced outage.
Interested power suppliers have
until July 29 to submit their expressions of interest, purchase bid documents
and pay a participation fee of P6 million.
A pre-bid conference will be held on
August 9.
The bids, together with a
P3.6-billion bid security, must be submitted on or before September 10. The
bids will be opened on the same day.
Last Friday (July 12), Meralco
published its first bid invite. The utility firm is soliciting 1,200 MW for 10
years starting December 26, 2019, up to December 25, 2029.
Interested bidders must pay a P2,500
fee per MW of offered contract capacity, submit an expression of interest and
confidentiality undertaking and purchase bid documents until July 26.
A pre-bid conference is scheduled on
August 8, with submission of bids set on September 9.
The CSP requires distribution
utilities (DUs) to hold competitive bidding for their supply requirements
as against securing power deals via bilateral contracts. This is meant to
ensure transparency and fair competition.
Meralco is expected to publish
another bid invite soon. This is the first of three invitations to bid
published. The three CSPs to be conducted are in accordance with the Power
Supply Procurement Plan that Meralco submitted to the Department of Energy
(DOE), Meralco utility head economics Lawrence Fernandez said in a text message
last week.
Meralco earlier inked seven PSAs
with several power generation companies, including subsidiary Meralco Power Gen
Corp. The total capacity of the seven PSAs is over 3,500MW.
However, these PSAs were not
implemented following the SC order which stemmed from allegations that the
Energy Regulatory Commission (ERC) gave due preference to Meralco by extending
the deadline for compliance with the CSP.
No comments:
Post a Comment