Published September 17, 2019, 10:00
PM By Myrna
M. Velasco
Luzon grid could be plunged into new
round of supply tightening starting the first week of October given the delay
on the commercial operations of the 500-megawatt San Buenaventura coal-fired
power project in Quezon province.
The plant’s commercial operation
date (COD), which was targeted September 15, had been pushed back because the
Energy Regulatory Commission (ERC) has not yet issued its certificate of compliance
(COC), the ultimate permit the facility needs so it can already move forward
into commercial operations.
The ERC, according to Meralco
President and CEO Ray C. Espinosa, raised questions on the water rights
accorded by the National Water Resources Board (NWRB), hence, the delay in
their ruling on the issuance of COC for the power plant’s operation.
Espinosa indicated they already
informed the Department of Energy (DOE) on the feared new round of supply
tightening next month because several plants will be on scheduled maintenance
shutdown.
And while some capacity will be out
from the system on their downtime, he emphasized that the San Buenaventura
plant will be an essential shield for spare consumers from brownouts or service
interruptions next month.
“We have alerted the DOE already
that there are scheduled outages already in October – as early as the first
week and we asked them to help us also to resolve this issue on water rights,”
the Meralco executive stressed.
He added that by the first week of
October, there are generating facilities that will be on shutdown and this will
result in 600 to 900 megawatts of capacity being taken out from the system.
“There are several plants that will
have their scheduled maintenance shutdown –so we’ve already planned for that,
but we should be very careful on supply. We have contracted plants, but this
San Buenaventura is important because this will add 455MW net capacity – and
you know supply is always tight,” Espinosa stressed.
Based on data that was submitted to
the DOE, the plants on scheduled outages will be: the unit 2 of the Ilijan
plant; San Lorenzo gas plant, one module of the Santa Rita gas plant, unit 2 of
Southwest Luzon Power Generation Corporation, unit 2 of the Masinloc plant; and
units 1 and 2 of the Sual plant.
The Malampaya gas production
facility will also be on scheduled shutdown from October 12-15, and almost
simultaneously, the 600MW unit 1 of the Ilijan gas-fired plant will be on
maintenance from October 3-15.
There were also several plants that
had been recently on forced outages including the Calaca unit 1, SMC
Consolidated Power Corporation, Sual Unit 2; and the South Luzon Thermal Energy
Corporation’s units 1 and 2 generating plants.
The power plants with de-rated
capacities include unit 2 of the Calaca plant, San Gabriel, Ilijan unit 2, and
Masinloc unit 2 facilities.
We CLOSED JOINT-STOCK COMPANY AGS OIL is one of the leading Oil & Gas trading companies in Russia Federation with good business reputation and well experienced in the Petroleum and mining sector. We offer the following trades through our reliable Refineries: D2 DIESEL OIL GOST 305-82, JP54 AVIATION KEROSENE COLONIAL GRADE, UREA 46%/PRILLS, LNG, LPG, REBCO, MAZUT100 GOST 10585-75/99, AUTOMOTIVE GAS OIL(AGO). We as well secure allocations from our various Refineries for our numerous buyers who are interested in Spot transactions on FOB/CIF deliveries to any world safe port (AWSP). Our Refineries have their products both at Russian ports and Rotterdam port. we also have a reliable SHIPPING COMPANY if you are in need of find the contact bellow.