By Lenie Lectura - September 17,
2019
Some 600 megawatts (MW) to 900 MW of
power-generating capacity will be shaved off from the Luzon grid next month due
to scheduled maintenance shutdown of some power plants, a top official of the
Manila Electric Co. (Meralco) said Monday.
Meralco President Ray Espinosa said
the scheduled maintenance shutdown of various power plants that supply the
utility firm will coincide with the four-day maintenance shutdown of the
Malampaya natural gas facility, which also supplies 40 percent of
Meralco’s requirement.
“We have alerted the DOE [Department
of Energy] already that there are scheduled outages already in October as early
as the first week. Within the first week, 600-900 megawatts will be out. That’s
scheduled but still, its good to have enough supply,” said Espinosa.
Data from Meralco showed that Ilijan
unit 1 (600 MW) will be on scheduled maintenance shutdown from October 3 to 15.
The same plant will also produced less capacity from October 16 to 18.
Other power plants that are on
scheduled shutdown next month are the 20-year-old Sual 2 (500 MW) from October
19 to November 17; San Lorenzo Module 50 (250 MW), from October 26 to 30.
The Malampaya gas facility,
meanwhile, will not be able to supply Meralco from October 12 to 15.
The gas facility fuels the following
gas plants: the 1,000-MW Santa Rita, the 500-MW San Lorenzo, the 1,200-MW Ilijan,
the 97-MW Avion and the 414-MW San Gabriel.
Meralco partly sources its
requirements from the Santa Rita, San Lorenzo, San Gabriel plants of First Gas
Corp. and from South Premier Power Corp.’s Ilijan plant. The utility firm does
not have a power-supply agreement with First Gen’s Avion plant.
Meralco head of utility economics
Lawrence Fernandez said the company is in coordination with the different power
plants that use Malampaya gas for fuel. During the shutdown, Santa Rita, San
Lorenzo and San Gabriel will be ready to run on liquid fuel so that their
capacities will continue to be available to the grid. The Ilijan
plant, meanwhile, will be on maintenance shutdown during the Malampaya
shutdown.
“We understand that the maintenance
shutdown activity will span four days and that half of the period will be over
the weekend,” he said.
Meanwhile, a DOE official said the
Malampaya shutdown is “not critical.”
“We are coordinating with
the system operator, the National Grid Corp. of the Philippines. They have
suggestions. It’s not critical because demand is not that big in October. It
will be well managed. There are gas plants that will run on diesel,
condensate,” said DOE Director Mario Marasigan who was present during the power-supply
agreement (PSA) signing of Meralco’s 500-MW contract capacity with power
producers.
DOE Assistant Secretary Redentor
Delola, in a text message, said the Luzon grid will have sufficient reserves
for the rest of the year due to decreasing demand and additional capacities
from new power plants coming online.
For Luzon, he cited the 300-MW
Masinloc expansion project set to commence this month and the 500-MW San
Buenaventura Power Ltd. (SBPL) project of Meralco Power Gen Corp. Both are
expected to inject power to the grid this month.
SBPL is a partnership
between MGen and New Growth BV, a wholly owned subsidiary of Electricity
Generating Public Co. Ltd. (EGCO Group) of Thailand.
However, SBPL’s 455-MW
coal-fired power plant in Mauban, Quezon, has hit a snag.
The country’s first coal-fired power
plant to use supercritical technology was supposed to start commercial
operation last September 15. The electricity to be generated by the
P56.2-billion plant will be sold to Meralco, the country’s largest distribution
utility, under a 20-year power-supply agreement.
Meralco was actually expecting this
power plant to supply its requirement starting next month. Espinosa said SBPL
is one of the plants listed under Meralco’s contingency plans when the
Malampaya gas facility is on shutdown.
“We have contracted plants but this
San Buenaventura is very important, it will at 455-MW net capacity and you know
supply is always tight, so we need additional capacity,” he said.
However, Meralco was lacking a
permit from the Energy Regulatory Commission (ERC). “We were targeting San
Buenaventura to go online, commercial operation date on September 15. But the
ERC has not yet issued the provisional authority to operate and the COC
[certificate of compliance]. Without those, San Buenaventura cannot go
online and supply power,” said Espinosa.
When asked to elaborate about the
permits, Espinosa said, “the ERC asked a question regarding the water use.”
“The water rights have been issued
in favor of Meralco by the National Water Regulatory Board and once it is in
the hands of a qualified Filipino, it can be used by anyone already. We were
really surprised about this. We have actually asked [DOE] to help us
also to resolve the issue of water rights,” said Espinosa.
This year’s Malampaya scheduled
maintenance shutdown will cover technical work at offshore platform (West
Philippine Sea) and at onshore gas plant (Batangas); repair of equipment;
installation of critical spare parts; check of instrumentation and controls.
“The shutdown will allow engineering
maintenance works at both onshore gas plant and offshore platform,” said Shell
Philippines Exploration BV (SPEx). “We are aiming to make shutdown duration as
short as possible to minimize impact to natural gas supply. This shutdown is
relatively short compared to previous ones.”
The Malampaya consortium is composed
of SPEx, with a 45-percent stake; Chevron Malampaya Llc., also with a
45-percent stake; and PNOC-EC (Philippine National Oil Co.-Exploration Corp.),
which holds the remaining 10 percent.
We CLOSED JOINT-STOCK COMPANY AGS OIL is one of the leading Oil & Gas trading companies in Russia Federation with good business reputation and well experienced in the Petroleum and mining sector. We offer the following trades through our reliable Refineries: D2 DIESEL OIL GOST 305-82, JP54 AVIATION KEROSENE COLONIAL GRADE, UREA 46%/PRILLS, LNG, LPG, REBCO, MAZUT100 GOST 10585-75/99, AUTOMOTIVE GAS OIL(AGO). We as well secure allocations from our various Refineries for our numerous buyers who are interested in Spot transactions on FOB/CIF deliveries to any world safe port (AWSP). Our Refineries have their products both at Russian ports and Rotterdam port. we also have a reliable SHIPPING COMPANY if you are in need of find the contact bellow.
ReplyDeleteEmail: baevsergeyalexandrovich@bk.ru
BAEVSERGEY ALEXANDROVICH.