By Lenie Lectura - March 11,
2018
POWER retailer Manila Electric Co.
(Meralco) has applied for a capital expenditure (capex) of about P21 billion
for 2019.
“I think we filed for something in
the order of about P20 [billion] to P21 billion. The capex for regulatory
year 2019 is in the order of about P21 billion,” Meralco President Oscar Reyes
said.
The amount P5.583 billion
higher than the capex it applied for the 2017 regulatory year, will be spent
mainly on enhancing the distribution network meant to handle the continued
growth in electricity demand.
“It’s primarily for network
requirements for load and customer growth because our number of customer base
continues to increase and the demand continues to increase, as well, so we have
to ensure that we have very resilient and hardened network,” Reyes said. “[By]
hardened [we mean it to be] in order to be able to meet the changes in
climate.”
He added Meralco’s capex is meant to
“serve the customer load growth, resiliency, safety and robustness including
hardening.”
Meralco’s capex for the
third regulatory year of its fourth regulatory period amounting to
P18.8 billion still awaits approval of the Energy Regulatory Commission (ERC).
The amount covers the period July 2017 to June 2018.
Capex in 2017 amounted to P12.1
billion, 5 percent higher compared with the previous year, with the partial
approval by the ERC of P24.2 billion out of the total P33.1 billion filed by
Meralco for the first regulatory year and second regulatory year of
the fourth regulatory period in June and July 2016, respectively.
The utility firm continues to
execute on the partial approved of capex, which allowed the addition of two new
substations, expansion of three existing substations and construction of an
additional 115 kilovolt (kV) line, among others.
More specifically, these completed
capex projects include the new Lucena and Pulilan substations, the additional
capacity in San Miguel, Balintawak and Veinte Reales substations, and the
additional 115-kV line from Paco substation.
In addition, three other significant
projects were completed. These were the replacement of the Malibay Power
Transformer Bank (PTB) 1, the uprating of the 115-kV power circuit breakers at
Balintawak and the replacement of the Urdeneta PTB 3, which was filed as an
emergency capex with the ERC.
Reyes said the challenges faced by
Meralco’s networks team include capex executions for system maintenance, load
and customer growth, network and customer service upgrading, weather hardening
and resiliency, safety and security, and automation.
Compounding these are the massive
poles and facilities relocation work required by the Department of Public Works
and Highways for road widening. A total of 1,771 electric poles affected by the
DPWH projects were relocated last year.
No comments:
Post a Comment