Danessa Rivera (The Philippine Star) - March 12, 2018 - 12:00am
MANILA, Philippines — Manila
Electric Co. (Meralco) is ramping up capital spending this year as it sees
continued growth in demand and increase in customer count.
Meralco president Oscar Reyes said
the power distributor plans to spend around P20- to P21-billion this year,
higher than the amount spent in 2017.
“The capex for regulatory year (RY)
2019 is in the order of about P21 billion,” he said.
He said the earmarked amount would
be used to finance requirements of its growing customer base and increasing
power demand within its franchise area.
The budget will also be used to
ensure resilient and hardened network to be able to meet the changes in
climate.
“We have to ensure that the capex is
something to serve the customer load growth, resiliency, safety and robustness
including hardening. Also, assess the requirements of customers for enhanced
services,” Reyes said.
The capital expenditure, however,
has to be approved first by the Energy Regulatory Commission (ERC).
Last year, Meralco sought P18.36
billion in capital expenditures (capex) to expand and upgrade its network in RY
2018 – which starts on July 1, 2017 and ends on June 30, 2018 – to meet
the growing power needs in its franchise area.
The capex application has yet to be
cleared by the power regulator.
In 2016, Meralco earmarked P15.4
billion capex for 23 major projects and 83 residual projects for RY 2017, but
the ERC only gave provisional authority for priority projects – nine major
projects and 37 residual project – in the amount of P8.76 billion.
This is to allow Meralco to
implement prioritized projects to ensure its ability to provide continuous safe
and reliable service to its customers.
For RY 2016, the ERC approved lower
capital spending for Meralco of P15.4 billion from its P17.5 billion to P18.5
billion original application.
Meanwhile, the company is still
hopeful that some of its long-term power supply agreements (PSA) still pending
with the ERC would be approved soon.
In April 2016, Meralco submitted
seven PSAs to the ERC, covering 3,551 megawatts, which corner 81 percent of the
combined output of seven power plants. However, nothing has been approved yet.
“They’re meant to meet additional
demand. Plants take five to six years to build from conception,” Reyes said.
Any further delay in the approval of
the power supply deals could translate to higher power rates for its 6.33
million customers in Metro Manila, Bulacan, Cavite, and Rizal, as well as
certain areas in Batangas, Laguna, Pampanga, and Quezon.
“We don’t want to create any sort of
fears or concerns but I think you just have to look at reality if you keep on
delaying projects. Demand is not stopping,” Reyes said.
The increase in contracted rates is
due to the negotiated costs with the engineering procurement contractor (EPC)
and bank financing were lower at the time deals were entered into, the Meralco
official said.
“We’ve been talking to them and
we’re asking them to stay aboard. But there are validity dates for our EPC,
financing,” he said.
No comments:
Post a Comment