By
Lenie Lectura - April 19, 2018
ENERGY
Secretary Alfonso G. Cusi on Wednesday said he prefers the power-generation arm
of Manila Electric Co. (Meralco) to undergo a Swiss challenge scheme for
the power-supply agreement (PSA) applications yet to be acted upon by
regulators.
“I’ll not speak on the
legal issues. My personal view is that they subject it to Swiss challenge. I am
not against Meralco…. I am looking for affordability. I am looking at the
tariff. I want assurance of supply. But, at the same time, I am going to make
sure that it is affordable and fair to everybody,” Cusi said.
The energy secretary
added he discussed this with Meralco PowerGen Corp. (MGen) President Rogelio
“Babes” Singson. “Babes told me that the PSAs are already pending with the ERC
[Energy Regulatory Commission],” the DOE chief said when asked for Meralco’s
reply.
Meralco’s PSAs
applications cover a total of 3,551 megawatts with various generation
companies (gencos).
These are with Redondo
Peninsula Energy Inc., St. Raphael Power Generation Corp., Atimonan One Energy
Inc., Central Luzon Premiere Power Corp. and Mariveles Power Generation Corp.
of the San Miguel Group and Global Luzon Energy Development Corp. of Global
Business Power Corp.
Meralco President Oscar
S. Reyes said these PSAs were entered into as early as April 2016. These
underwent all the necessary due process, including documentation
and public hearings.
However, the ERC
allegedly favored Meralco by excluding the power-distributor from
the competitive selection process (CSP), which requires distribution
utilities and power-generation companies to subject their PSAs to price
challenges.
This did not sit well
with consumer groups and other sectors. Lawmakers conducted an inquiry into the
alleged midnight deals for Meralco.
The agency denied this.
The ERC extended the validity of the CSP policy mainly because it wanted
to address the valid concerns raised by the distribution untilies and gencos.
“The extension of the CSP implementation was not intended to benefit any
electric power industry participant, but to give time to those who have already
completed their PSAs but failed to submit the same to the ERC prior to the
effectivity of the CSP,” the ERC said.
The delay in the
approval of these applications and the consequent delay in the financial close
and, subsequently, the commercial operations date of the power projects will
adversely affect the utility firm’s ability to meet demand growth in its
franchise and overall energy security in the Philippines.
“I am not going to
demand something that is not legal,” Cusi added when asked if shifting the
procurement process to Swiss challenge from CSP is legal.
“It did not go through
CSP, that’s the issue. So have it undergo via Swiss challenge,” Cusi said.
Reyes said ERC approval
is urgently needed, saying the delay has caused significant increases in the
engineering, procurement and construction (EPC) costs and financing costs of
the new power plants.
The Meralco official
said that if the total costs of the projects were to balloon, then the
financing cost would increase, as well. “It would be most unfair to Meralco
customers,” Reyes said.
“Costs have been
increasing,” he added. “We negotiated very competitive EPC costs. We negotiated
competitive costs and also financing terms. I don’t think we can repeat
it.”
Reyes could not stress
enough the importance of the PSAs, which, he said, are meant to meet additional
electricity demand. “We don’t want to create any sort of fears or concerns, but
I think you just have to look at reality if you keep on delaying projects.
Demand is not stopping,” the Meralco official said.
For now, all Meralco
could do is to “continue to make our case and appeal for timely action and
decision.”
“Our option is to
continue to hope,” Reyes said.
No comments:
Post a Comment