By Lenie Lectura - June 28, 2019
ENERGY Secretary Alfonso Cusi said
on Thursday the Manila Electric Co. (Meralco) has informed him the utility firm
would conduct no later than end-June a competitive selection process (CSP) of
its power requirements.
“For the building capacity, I’d like
to inform you that we have sat down with Meralco and we are going to already
subject to CSP around 2,000 megawatts [MW] by the end of this month. It will be
published already in the newspaper of national circulation for CSP to comply
with the requirement of the Supreme Court ruling that was passed last month,”
Cusi said.
When sought for comment, Meralco
Spokesman Joe Zaldarriaga said the utility firm is “closely following the DOE’s
CSP guidelines and will publish very soon the invitations to bidders to supply
power to Meralco,”
Meralco, he added, would bid out
“what the system needs in terms of load requirements” and that it would not
matter which technology is preferred. “Technology agnostic. Hindi planta ang
uunahin namin; capacity requirements muna,” Zaldarriaga stressed.
The energy chief met Meralco
officials on June 13. The meeting was meant to remind Meralco that the CSP must
be conducted soon in a bid to ensure a reliable and steady supply of energy.
“We must act fast because demand
continues to grow and we want to be ready to supply the needs of a growing
market to ensure that the country will maximize its growth potential,” Cusi
said.
Under the CSP, electric cooperatives
and distribution utilities must conduct a bidding for the contract of its power
supply to ensure transparency and fair competition.
This developed after the release of
the SC decision stating that “all Power Supply Agreement [PSA] applications
submitted by Distribution Utilities [DUs] to the Energy Regulatory Commission
[ERC] on or after June 30, 2015 shall comply with the CSP based on DOE’s 2018
Department Circular.”
The DOE guidelines state that the
form of CSP should be bidding or auction, not price challenge.
Over 90 PSA cases are covered by the
SC decision. Seven of which are PSAs entered into between Meralco and several
power producers, including with Meralco’s power generation arm, MeralcoPower
Gen Corp. (MGen).
These seven PSAs make up about 3,500
MW in total capacity.
Meralco’s PSA are with two
subsidiaries of MGen, which is building power plants under Redondo Peninsula
Energy Inc. and Atimonan One Energy Inc. It also has a PSA with St.
Raphael Power Generation Corp., its joint venture with Consunji-led SMPC.
Meralco earlier inked PSAs with
Central Luzon Premiere Power Corp., Mariveles Power Generation Corp., Panay
Energy Development Corp. and Global Luzon Energy Development Corp.
Atimonan One Energy Inc.’s first 2x
600MW power plant was already certified by the DOE as an Energy Project of
National Significance.
MGen noted that if this power
project had been approved on time, then at least 600 MW would have been added
to the grid this year.
“We have already reached in April
the peak demand level that was recorded in May last year. At least 626 MW is
needed and this is just about the estimate that the DOE keeps on saying. So,
the DOE is right in saying that we need new capacity of 600MW every year as
demand keeps rising,” MGen president Rogelio Singsgon noted.
Singson said Thursday MGen would
participate in the CSP.
No comments:
Post a Comment