Published
November 1, 2017, 10:00 PM By
Myrna M. Velasco
A milestone level of
generation of 600 giagawatt hours (GWh) has been reached by the 20-megawatt
(MW) Maibarara geothermal power facility, according to the PetroEnergy
Resources Corporation, the major equity holder firm in the project’s corporate
vehicle.
That magnitude of
generated capacity was officially clocked in October 25 this year, barely three
years and eight months from the start of commercial operations of the power
facility.
Plant operator
Maibarara Goethermal, Inc. (MGI) emphasized that such achievement manifests
array of efficiency in the facility’s operations, including plant outages being
kept down.
As emphasized by MGI
President Francisco G. Delfin, “apart from the scheduled annual maintenance
shutdowns, we have managed to minimize forced outages in the facility leading
to very high capacity and availability factors.”
The project, which was
recently conferred the much-coveted 2017 ASEAN Energy Awards being the Best
Renewable Energy Project, was considerably a new development in an era when
extraction of geothermal resources in the Philippines had already been turning
a lot tougher.
It was a lull of 16
years of development in the sector before the Maibarara project came into
fruition at commercial development phase; and was also considered a take-off
point venture on that technology space since the passage of the country’s
Renewable Energy Act.
The facility under MGI
was a joint development of PetroGreen Energy Corporation of the Yuchengco
Group, PHINMA Energy Corporation and that of state-run Philippine National Oil
Company-Renewables Corporation.
The plant is currently
advancing on its expansion phase for another 12MW capacity, targeted to be on
commercial stream by December this year.
According to Paul
Morala, MGI power plant manager, a revenue meter had just been installed
recently at the Maibarara-2 geothermal project, indicating then that the asset
is now moving headway into its full commercial operation.
The company executive
added that the engineers of MGI and Manila Electric Company (Meralco) have also
jointly and successfully completed the testing of the plant’s protection relays
and circuit breakers; and also of the unit’s supervisory control and data
acquisition (SCADA) and direct transfer trip (DTT) functions.
Morala said their
collaboration with the concerned industry entities as well as with the relevant
government agencies, such as the Department of Energy and the Energy Regulatory
Commission, will continue “as the unit’s commissioning and testing enter their
final phases.”
No comments:
Post a Comment