(The Philippine Star) | Updated October 30, 2017 - 12:00am
MANILA, Philippines —
The National Grid Corp. of the Philippines (NGCP) is earmarking P12.41 billion
to put up new transmission projects to support the increasing demand for
electricity in Bohol and Boracay as well as improve the reliability of the
electrical system of the Visayas grid.
NGCP is seeking the
approval of the Energy Regulatory Commission (ERC) for the Cebu-Bohol
230-kilovolt (kv) Interconnection Project and the Nabas-Caticlan-Boracay
Transmission Line Project.
The Cebu-Bohol project
is estimated to cost P8.14 billion and will take 50 months to construct. A
budget of P4.27 billion is allocated for the Nabas-Caticlan-Boracay project,
which will take 35 months to build.
“A system collapse is
imminent and will be experienced as early as 2021 if the projects are not
undertaken. It must be emphasized that the implementation periods of the
projects are 50 and 35 months for the Cebu- Bohol and Nabas-Caticlan-Boracay,
respectively. Thus, it is necessary for us to immediately commence the
implementation of the proposed projects,” NGCP said.
In its application,
NGCP said the Cebu, Leyte and Bohol islands are interconnected through the
Cebu-Leyte 230-kv and Leyte-Bohol 138-kv submarine cables, with the latter
having a capacity of only 90 megawatts (MW).
“To avoid the expected
overloading of the Leyte-Bohol submarine cable, NGCP proposes to interconnect
the Cebu and Bohol Islands through a 230 kV submarine cable,” it said.
Bohol gets its power
supply from Leyte since the several hydro and oil-based power plants in the
island are not enough to meet its power requirements.
The grid operator said
that by 2020, Bohol’s demand would reach 89 MW which would further increase to
95 MW by 2021. This will put pressure on the existing submarine cable between
the two islands.
“With the
interconnection, the overloading of Leyte-Bohol 138 kv submarine cable will be
avoided, and will provide the Bohol Island with another source of power coming
from Cebu,” NGCP said.
Meanwhile, NGCP said
power demand in Boracay would exceed the capacities of existing transmission
facilities serving the island.
Boracay is being served
by the Nabas Substation through the single-circuit Nabas- Caticlan-Boracay
69-kv overhead line and submarine cable system.
Power demand in Boracay
has already exceeded the capacity of the existing transformer in Manoc-manoc
load-end substation this year and will exceed the capacity of the
Caticlan-Boracay 69-kv submarine cable by 2018.
“The same simulation
also clearly shows that by 2021, the cumulative demand of the load-end
substations in Caticlan and Boracay will exceed the capacity of the 69-kv line
from Nabas Substation which will result to system collapse,” NGCP said.
No comments:
Post a Comment