ABOITIZ Power Corp. was informed by its wholly-owned subsidiary Aseagas Corp. that the latter will continue the shutdown of its 8.8-MW biomass power plant in Lian, Batangas to further assess the plant’s technical problems and determine the appropriate way forward for the facility. The Lian plant earlier ceased operations due to unavailability of the supply of organic effluent wastewater from Absolut Distillers, Inc. Aseagas also disclosed yesterday today that it pre-paid its outstanding loan with the Development Bank of the Philippines (DBP) in the amount of P2.368 billion. Aseagas also has invested equity of around P950 million for the biomass plant, and has around P460 million in outstanding liabilities. (PR)