By
Lenie Lectura - December 3, 2017
THE National Grid Corp.
of the Philippines (NGCP) seeks approval of the implementation of additional
capital expenditures (capex) in the amount of P62.32 billion to be spent until
2020 for various transmission projects.
In a 12-page
application filed before the Energy Regulatory Commission (ERC), the grid
operator said the amount covers 23 vital grid expansion and reliability
projects, bulk of which will be in Luzon.
Of the total amount, 12
additional projects worth P33.271 billion are programmed for Luzon; seven for
the Visayas at a cost of P15.7 billion; and five projects in Mindanao worth
P13.35 billion. The most expensive project in Luzon is the development of the
Tuy 500/230 kiloVolt (kV) substation (Stage 1), which will serve as the
connection point of the 2×350-megawatt (MW) plant of Saint Raphael Power
Generation Corp. and other future generation additions in the area. The
project, estimated to cost P8,454.09 million, will have a 34-month
implementation period.
Meanwhile, the Laray
230-kV substation project worth P5,029.49 million, is the most expensive in the
Visayas, with project implementation set at 38 months. The San Francisco-Tandag
138-kV transmission line project is the most expensive in Mindanao. The
estimated cost for the project is P4,198.64 million and the implementation
period is 48 months.
The NGCP, which
originally filed for approval of a P113.4-billion capex for 2017 to 2020, is
required to seek prior approval from the ERC of any plan for expansion or
improvement of its facilities in relation to its authority to construct,
install, finance, improve, expand, rehabilitate and repair the nationwide
transmission system and the grid. The four-year budget application is still
pending with the commission. The capex for 2017, however, was approved at P5.5
billion.
Along with its
responsibility for the planning, construction and centralized operation and
maintenance of its high-voltage transmission facilities, it is indispensable
for the NGCP to ensure a reliable and high-performance operation of the
transmission system.
“Thus, to avoid
disruption of operation and ensure continuous compliance with the NGCP’s
mandate under the Epira [Electric Power Industry Reform Act]as the
transmission operator, it is imperative that the implementation of the proposed
capex projects be immediately approved,” the grid operator said in its
application.
No comments:
Post a Comment