(The Philippine Star) | Updated December 8, 2017 - 12:00am
MANILA, Philippines —
The Malampaya deepwater gas-to-power project can still supply gas up to 2029,
but operators need to hurdle the tax dispute with the Commission on Audit (COA)
to be able to extend its contract beyond 2024, a ranking official said.
The Malampaya project
still has gas supply beyond the expiration of its contract in 2024, Shell
country manager Cesar Romero said in an interview with reporters late
Wednesday.
“Based on what we know
(and) depending on the drawdown, we still have supply until 2027 to 2029,
within that range,” he said.
The license for Service
Contract (SC) 38 that allows the exploration of the Malampaya gas field in
northwest Palawan will expire in 2024 but this can be applied for extension
with the Department of Energy (DOE).
Shell Philippines
Exploration B.V. (SPEX), a local unit of energy giant Royal Dutch Shell, leads
the Malampaya consortium with 45 percent, Chevron Malampaya LLC with another 45
percent and PNOC Exploration Corp. (10 percent).
Even if Malampaya will
still be able to supply beyond 2024, the government will still proceed with its
$2-billion liquefied natural gas (LNG) terminal, DOE Secretary Alfonso Cusi
said yesterday.
The country’s
integrated LNG hub should consist of five million metric tons per annum (MTPA)
of storage, liquefaction, regassification and distribution facility, as well as
a reserve initial power plant capacity of 200 megawatts (MW).
It is targeted to be
operational before 2022, or before the depletion of the Malampaya gas project.
It is also envisioned to make the Philippines an LNG hub for Asia,
complementing those in Japan and Singapore.
However, to be able to
extract available gas, Romero said the consortium still has to resolve its tax
issue with COA, which said the project has a tax deficiency amounting to
billions of pesos.
Once hurdled, only then
can Shell firm up investments to extend the Malampaya contract, he said.
“We’re in discussions
with government on how it goes. So far, why it’s so difficult to think about
these things is the COA case is still pending. It’s difficult to make concrete
plans until you are able to sort out the issue with COA,” Romero said.
“Any action we think
about at the moment is put on hold because we have to sort out COA first,” he
said.
The SC 38 consortium
earlier expressed interest to extend its license to explore for oil and gas in
northwest Palawan until 2039.
In 2012, the consortium
embarked on a P1-billion expansion program for the Malampaya project through
two new project phases, which was completed in 2015.
This expansion will
maintain the level of gas production to fulfill commitments under existing gas
sales agreements until 2024, ensuring the steady supply of natural gas to power
the Luzon electricity grid.
But in an April 6, 2015
decision, COA upheld its 2009 findings that more than P50 billion were
uncollected by the consortium operating the Malampaya project.
SPEX has filed two
arbitration cases over its P53.14-billion tax dispute from the Malampaya
project — one with Singapore International Arbitration Center in Singapore in
late 2015 and another with International Center for the Settlement of
Investment Dispute in July 2016.
The gas field has
proven reserves of 2.7 trillion cubic feet to 3.2 TCF, of which around one TCF
has already been consumed.
Operating since 2001,
the Malampaya gas project supplies fuel to around 40 percent of gas-fired
plants in Luzon namely the Ilijan, Sta. Rita plant, San Lorenzo, San Gabriel
and Avion plants — which supply 3,211 megawatts to the Luzon grid.
No comments:
Post a Comment