October 7, 2019 | 12:03 am By Victor V. Saulon
FIRST GEN Corp. targets
to lease a floating storage regasification unit (FSRU) for liquefied natural
gas (LNG) early next year when it has determined the volume that it needs to
import fuel to existing power plants and potential capacity expansion, its top
official said.
“Until we know what we
need, that’s when we can contract. So when we do that, is probably some time
first quarter of next year,” said First Gen President and Chief Operating
Officer Francis Giles B. Puno in an interview.
He said the standard
storage size of an FSRU is about 120 metric tons (MT) to about 150-160 MT. But
the volume should also factor in the number of times transport ships will be
bringing in LNG from foreign sources, and the volume of gas used by the
existing power plants.
“There are
international service providers that can provide the floating storage regas
unit itself. There are many vendors that do that,” he said, adding that the
company is in talks these vendors. “That discussion has been there for some
time already as well.”
Mr. Puno said the “base
case” today for First Gen remains the construction of an onshore LNG import
terminal.
In December last year,
the company signed a joint development agreement with Japan’s Tokyo Gas Co.,
Ltd. to build the terminal within the Lopez-led company’s power generation
complex in Batangas City.
In September this year,
First Gen named Japan’s JGC Corp. as the engineering, procurement and
construction contractor. The immediate focus of the partnership is to complete
a detailed study to modify the existing jetty in Batangas to accommodate large-
and small-scale LNG vessels, while continuing to receive liquid fuel.
First Gen, the
country’s leading gas power generation company, has around 2,000 megawatts (MW)
in operating gas facilities comprising of four gas-fired power plants, namely:
the 1,000-MW Santa Rita power plant, the 500-MW San Lorenzo, the 414-MW San
Gabriel, and the 97-MW Avion power plant.
Mr. Puno said site
preparations for the onshore terminal had been completed.
“Then we’ll build the
jetty — the reconfiguration of the existing jetty. So now that’s going through
detailed studies,” he said.
Feasibility studies
will help configure the jetty to accommodate the FSRU, which is a big vessel
that will be permanently docked.
“We’re studying that to
see if there’s any fatal flaw, technical specification that needs to be done to
essentially adjust the existing jetty that we have. So that will determine also
the size of the ship that we can bring in,” he said.
First Gen targets to
start using the FSRU in 2021, although it has an existing contract with the
consortium behind the country’s Malampaya gas until 2024.
Mr. Puno said there are
times when Malampaya gas capacity is “maxed out” thus the need to buy imported
LNG towards the end of the concession when there might be uncertainty on the
reliability of the home-sourced natural gas.
“They (Malampaya
consortium) need to reinvest. So whereas before we were planning to construct
and hopefully start operating the onshore terminal by 2024, the floating
storage allows us to accelerate that sooner just in case, for example,
Malampaya is not enough,” he said. “It also allows us to expand quicker, like
build more capacity potentially.”
He said the FSRU would
allow the company to take advantage of the current market situation where the
price of gas is “cost competitive.”
“At some stage, we’re
hoping that we can even import gas at a price that is at least equal if not
cheaper than the existing Malampaya. So that’s also good for the consumers,” he
said.
The existing gas
contract with Malampaya only has the Santa Rita and San Lorenzo plants under a
“firm” deal. For the San Gabriel and Avion plants, the contract is “flexible.”
Mr. Puno said plants
under the flexible contract would “potentially” use the imported LNG. “Or maybe
new capacity. That’s one. And secondly, we also have Ilijan, ‘yung sa
San Miguel [Corp.], which will expire in 2022, I believe. So in two years’
time, they will need more gas as well.”
“Right now, we’re also
in discussion with them (San Miguel) on being able to sell gas to Ilijan,” he
said.
First Gen has
identified “numerous” LNG suppliers, which are kept engaged in the discussions,
Mr. Puno said. He said locking in a contract at this time would be premature.
Mr. Puno also said that
the company’s dollar commitment for imported gas is an even bigger number than
the investment for the regasification infrastructure, but did not disclose
figures.
“Once the demand is
already firmed up then we can contract. And contracting really is not that
difficult. The question really is do we have the infrastructure to bring in the
gas and then utilize that,” he said.
He said First Gen is
looking to initially contract with gas suppliers for the FSRU, which is a
smaller volume than that for the onshore facility.
“Anyway, the contract
for Santa Rita and San Lorenzo will only expire in 2024. We don’t need as much
gas today than in 2024. In 2024, definitely we’ll need the gas,” he said.
No comments:
Post a Comment