Tuesday, October 15, 2019

Plant outage prompts NGCP to issue ‘yellow alert’ in Luzon grid on Monday


By Lenie Lectura - October 15, 2019

THE Luzon grid was placed on “yellow alert” for six hours on Monday, with over 4,000 megawatts (MW) of capacity shaved off from the grid mainly due to unplanned outage of several power plants.
Data from the Department of Energy (DOE) showed that a total of 4,744 MW of capacity was unavailable, prompting the National Grid Corp. of the Philippines (NGCP) to issue the yellow alert notice effective 10:01 a.m. until 4 p.m.
A yellow alert is issued when operating reserves have dropped below the required 647 MW contingency in Luzon, or equivalent to the largest unit in Luzon, which is the 647 MW coal-fired power plant in Sual, Pangasinan.
“We are closely monitoring the situation. The DOE’s power bureau is on top of this,” said Energy Undersecretary Felix William Fuentebella said in a text message.

Unplanned outage
Avion natural gas plant units 1 (50 MW) and 2 (50 MW), Sual (647 MW), San Jose biomass plant (12 MW), GN Power Mariveles coal plant (345 MW) and Tiwi geothermal plant unit 1(60 MW) underwent forced outage.
The two units of Avion went offline since August due to gas turbine leak, while GN Power coal plant was unavailable since September 20.
The geothermal plant of AboitizPower has been has not been delivering power since November last year.
Sual and San Jose biomass plants underwent emergency shutdown on October 11 and 13, respectively, due to technical glitches.
While Malaya power plant unit 1 (150 MW), MakBan (55 MW) geothermal plant and the power facilities Ilijan blocks A (600 MW) and B (600 MW), San Gabriel (420 MW), which source fuel from the Malampaya gas facility are on Outside Management Control (OMC) outage.
“An Outside Management Control Outage is an outage wherein the cause is beyond the control of the generation company, and has not resulted from planning error or negligence,” according to Fuentebella.
For geothermal plants, he explained that the term OMC means the issue is the lack of steam. For gas plants, there was lack of gas supply due to the Malampaya shutdown. For Malaya, Fuentebella said, “it’s a must-run plant, hence it also falls within the term.”
In all, these power plants that are on forced outage and on OMC outage make up 2,955MW, or 62.3 percent, of the total unavailable capacity.

Malampaya shutdown
The gas facility, which supplies 40 percent of Manila Electric Co.’s (Meralco) requirement, was not able to fuel the gas plants from October 12 to 15.
The gas facility fuels the following gas plants: the 1,000-MW Santa Rita, the 500-MW San Lorenzo, the 1,200-MW Ilijan, the 97-MW Avion and the 414-MW San Gabriel.
The operator of the gas facility said the four-day shutdown would allow engineering maintenance works at both onshore gas plant and offshore platform.
“The Malampaya scheduled maintenance shutdown activities started last Saturday morning and progressing as planned until tomorrow evening. Gas delivery to customers start early morning of Wednesday,” an official of Shell Exploration BV, which leads the Malampaya consortium, said via text message.
Meralco head of utility economics Lawrence Fernandez said that while the Ilijan plant and San Gabriel plant (420 MW) are on shutdown during the period, the Santa Rita and San Lorenzo power plants will run on liquid fuel and continue to supply power to the grid.
“We have called on ILP [interruptible load program] participants to prepare to be activated, if the supply situation deteriorates, but we hope that no other generator goes on ‘unplanned’ outage at this time,” he said in an interview.
Meralco partly sources its requirements from the Santa Rita, San Lorenzo, San Gabriel plants of First Gas Corp. and from South Premiere Power Corp.’s Ilijan plant. The utility firm does not have a power-supply agreement with First Gen’s Avion plant.

Derated capacity
Contributing the to the grid’s thin power reserves are the derated capacities of SEM-Calaca from 300 MW to 200 MW, Angat hydro plant from 200 MW to 160 MW and the Pantabangan hydro plant (120 MW).
The DOE also recorded 1,349 MW of derated capacity from various power plants. The agency did not provide a list of these plants. In all, 1,609 MW of capacity was not delivered to the grid because of derated power plant capacity.
Also, included in the DOE data is the planned outage of CBK hydro plant unit 3 (184 MW).

’Not critical‘
Earlier, a DOE official said the Malampaya shutdown would not affect the grid’s integrity.
“We are coordinating with the system operator, the National Grid Corp. of the Philippines. They have suggestions. It’s not critical because demand is not that big in October. It will be well managed. There are gas plants that will run on diesel, condensate,” said DOE Director Mario Marasigan.
Energy Assistant Secretary Redentor Delola, in a text message, said the Luzon grid will have sufficient reserves for the rest of the year due to decreasing demand and additional capacities from new power plants coming online.
For Luzon, he cited the 300-MW Masinloc expansion project which is set to commence this month and the 500-MW San Buenaventura Power Ltd. project of Meralco Power Gen Corp. Both are expected to inject power to the grid this month.
SBPL is a partnership between MGen and New Growth BV, a wholly owned subsidiary of Electricity Generating Public Co. Ltd. (EGCO Group) of Thailand.

No comments:

Post a Comment