By: Riza T. Olchondra 01:31 AM June 20th, 2016
CLEANTECH Global Renewables Inc. is
set to spend up to $1 billion on solar power projects to complement its
hydroelectric power pipeline.
Company president and CEO Salvador
Antonio Castro Jr. said the company wanted to build up solar capacity to 500
megawatts (MW) over the next five years. This will entail investments of $750
million to $1 billion, he said.
The renewable energy (R.E.)
developer also has a pipeline of hydroelectric power projects worth $400
million, according to Castro.
Cleantech is keen on applying for
feed-in-tariff (FIT) incentives for its solar power plants, he said.
Cleantech has completed the first
phase of its solar power plant rollout. “We’ve developed a 15 MW solar farm in
San Ildefonso, Bulacan, under the SPV (special project vehicle) name Bulacan
Solar Energy Corp. (BSEC),” Castro said.
The project, which can be expanded
with another 35 MW, is in a franchise area of Manila Electric Co. and cost
about $30 million.
The BSEC solar farm is in a
25-hectare property in Barangays Pasong Bangkal and Casalat, San Ildefonso,
Bulacan.
The solar power plant in San Ildefonso
was energized on March 12 and operated successfully for three days, which is a
requirement for a solar power plant to be considered for FIT incentives, Castro
said.
He expressed confidence the project
would be considered for FIT incentives since the deadline for solar was March
15.
Castro said firm plans for solar
power include work on a service contract for another 85 MW in Bulacan and
another 100 MW in Pangasinan.
For the 85-MW and 100-MW power plant
projects to be developed, Castro said the company was open to bilateral
contracts but being able to operate in the spot market with FIT incentives
would be a more viable business model.
The regulator-approved FIT rates are
P6.63 per kilowatt-hour (kWh) for biomass, P5.90 per kWh for hydro, P8.53 per
kWh for first phase of wind and P7.40 per kWh for second phase of wind, and
P9.68 per kWh for first phase of solar, P8.69 per kWh for the second phase.