posted June 20, 2016 at
11:35 pm by Alena Mae S. Flores
Energy World Corp.
committed to commission the first 200-megawatt unit of the 650-MW liquefied
natural gas combined cycle power plant in Pagbilao, Quezon by the end of the
year.
Energy Department
director Irma Exconde of the Electric Power Industry Management Bureau said EWC
was supposed to commission the first unit within six months.
“The commissioning date
of the first 200-MW gas turbine is six months after drawdown of the funds,” she
said, quoting the letter of EWC to the department.
EWC said on June 14 it
achieved drawdown of the P1.5-billion funds for the Pagbilao LNG hub terminal
project, which meant the project was expected to be completed by Dec. 14.
The company’s omnibus
loan and security agreement provides an additional P2-billion facility for the
project.
Standard Chartered Bank
acted as issue manager and bookrunner while Land Bank of the Philippines was
the lead arranger of the loan.
Energy undersecretary
Mylene Capongcol earlier said tEnergy World’s natural gas plant power facility
could not deliver power to the Luzon grid despite being completed.
“They are having
interconnection problems,” Capongcol said.
Capongcol said Energy
World’s planned floating storage regassification unit, which was supposed to be
the first LNG facility in the country, remained to be completed.
Reynaldo Umali,
chairman of the House committee on energy, also said a team from the committee
visited the company’s project and learned about the interconnection issues
hounding the project.
“There’s a problem in
the interconnection. But the plant itself can produce anytime. It’s ready for
commissioning, except for the interconnection concerns,” Umali said.
Energy World previously
targeted to complete the first 200-MW unit by March. The second 200-MW unit was
supposed to be in commercial operation by June.
The company will
initial source LNG from a floating, storage and regassification unit, pending
the completion of an LNG terminal.
The company earlier
said the LNG hub would primarily facilitate the distribution of LNG and natural
gas, including receipt, storage and dispatch of LNG cargoes to four main
markets, namely the Energy World plant, small-scale terminal, LNG and
compressed natural gas for fuels and other markets in Asia Pacific.
No comments:
Post a Comment