Published
By Myrna M. Velasco
State-run National
Power Corporation (NPC) has already completed rehabilitation works at the
spillway area of the San Roque dam in Pangasinan, a facility yielding
435-megawatt power capacity to the Luzon grid.
The power company said
the completion of that rehab work will guarantee “the integrity of the
200-meter tall facility,” which straddles the Agno River in the northern part
of the country.
The cost of the
project, according to NPC, was at R275 million. The decision to pursue it
was arrived at “after traces of erosions were discovered at the base of the
dam’s spillway,” the power firm stressed.
Investment in the
restoration work at the dam, it was further noted, was split accordingly
between NPC, the Power Sector Assets and Liabilities Management Corporation
(NPC) and plant operator San Roque Power Corporation.
NPC emphasized that
based on their findings, “erosions were caused by scouring which was aggravated
by extreme typhoons that hit the dam” in previous years – primarily those of
typhoons Ineng and Lando.
As noted by NPC
President and Chief Executive Officer Pio J. Benavidez, “the rehabilitation
project was immediately bid out and implemented in January of last year to
avoid further erosion and increased rehab cost.”
If culled from the
company’s timeframe on the work program, Benavidez pointed out that they were
able to top it, as completion was achieved three months ahead of schedule –
that was in the last quarter of 2017.
It has been emphasized
that the relevant entities in the San Roque hydropower complex’s operations
“ensure the satisfactory condition and integrity of the dam through conduct of
separate inspection and assessments.”
The San Roque project
serves three functions in meeting the country’s need for water quality
improvement, flood control and irrigation as well as electricity generation.
It was undertaken
through a build-operate-transfer (BOT) scheme and had started delivering power
to Luzon grid in 2003.
And in line with the
privatization of NPC power assets prescribed under the Electric Power Industry Reform
Act (EPIRA), its power supply contract had eventually been placed under the
charge of San Miguel Energy Corporation’s subsidiary as Independent Power
Producer Administrator.
No comments:
Post a Comment